PINATAR (102.5 MWp) IS NOW ENERGIZED

During the first week of June 2026, we successfully energized PINATAR, the largest photovoltaic plant ever developed, designed, and built by GRUPO ZARAGOZÁ.

Located in Casas Blancas (Murcia), the project features:

  • 102.5 MWp of installed peak capacity
  • 206,550,156 kWh of estimated annual production
  • Capacity to supply electricity to 63,127 households
  • 164,647 tonnes of CO₂ emissions avoided per year

 

The plant covers 144 hectares, an area equivalent to nearly 200 football fields, and represents a major milestone for our company.

With the energization of PINATAR, we have completed the construction phase and are now entering the operation and maintenance stage.